Construction Impacts

Road and Parking Lot closures, Ivy/Western Way, starting Dec. 22
Dec. 16, 2021
Author
Written by csuter

As of December 22, 2021, construction crews will begin preparations to close Ivy Lane and Western Way to vehicular traffic on campus between…

Noise & Vibrations, around Princeton Stadium, 1 month
Nov. 24, 2021
Author
Written by csuter

As part of construction for our new ES & SEAS Utility Tunnel Project, we need to enable excavation by removing below-grade rock. The rock will…

Sidewalk Closures, at Washington & Ivy, 2-3 months
Nov. 1, 2021
Author
Written by csuter

Various sidewalks need to close in front of Lewis Library, at the Washington/Ivy intersection, due to underground work that will take place…

Walkway closures, North Garage
Oct. 19, 2021

On 10/19 and 10/22, the pedestrian walkway at the northeast corner of the garage will be closed with a barricade, preventing pedestrian traffic…

Roof closed, North Garage
Oct. 16, 2021

North Garage roof will be inaccessible starting October 11 through late December due to the installation of solar panels.

When the…

Sidewalk Closures, by Ferris Thompson Apts, 4-5 months
Sept. 7, 2021
Author
Written by csuter

Effective today, the north sidewalk of Ivy/Western Way needs to close for approximately 4-5 months due to the loss of power to the north side…

Road closed, Fitzrandolph, until Aug 2022
April 16, 2021
Author
Written by csuter

UPDATE 2: Fitzrandolph will remain closed through August, 2022.

UPDATE: Fitzrandolph will remain closed until March 4, 2022. Faculty Road…

Road Closure, Stadium Drive
April 16, 2021
Author
Written by csuter

Stadium Drive needs to close due to underground utility work for the Steam to Hot Water Conversion project. Pedestrian access to…